Original Cost
₹419 Cr
Baseline estimate
Revised Cost
₹419 Cr
Latest approved cost
Expenditure
₹423 Cr
Spent to date
Utilization
100.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Spent
₹423 Cr
Remaining
₹0 Cr
Total
₹419 Cr
Project Approved
Construction / Implementation
Original End Date
16/02/2020
Revised Completion
15/03/2024
Completed
Project is within original budget of ₹419 Cr — no cost escalation recorded.
Expenditure stands at ₹423 Cr, which is 100.9% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.