Roads & HighwaysIPM · Central Project#617968

Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 Augustmuni to Kund & Guptkashi to Sitapur on NH 109 in UK

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹419 CrUtilization: 85.5%

Original Cost

₹419 Cr

Baseline estimate

On budget

Revised Cost

₹419 Cr

Latest approved cost

Expenditure

₹358 Cr

Spent to date

Utilization

85.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹61 Cr

Budget left

Budget Utilization

85.5%
0%25%50%75%100%

Spent

₹358 Cr

Remaining

₹61 Cr

Total

₹419 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

16/02/2020

Revised Completion

15/03/2024

Completed

Project Details

Project Code617968
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹419 Cr
Revised Cost₹419 Cr
Expenditure₹358 Cr
Original End Date16/02/2020
Revised Date15/03/2024

Project Intelligence

Project is within original budget of ₹419 Cr — no cost escalation recorded.

Expenditure stands at ₹358 Cr, which is 85.5% of the revised project cost.

Remaining budget: ₹61 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 Augustmuni to Kund & Guptkashi to Sitapur on NH 109 in UK is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹419.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to "?
Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 Augustmuni to Kund & Guptkashi to Sitapur on NH 109 in UK is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹419 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹419 Cr has not been significantly revised. Expenditure: ₹358 Cr (85.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction & Widening Including Augustmuni Bypass Ch-16.54 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617968. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction & Widening Including Augustmuni Bypass Ch-16.54 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.