Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 Augustmuni to Kund & Guptkashi to Sitapur on NH 109 in UK
Original Cost
₹419 Cr
Baseline estimate
Revised Cost
₹419 Cr
Latest approved cost
Expenditure
₹358 Cr
Spent to date
Utilization
85.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹61 Cr
Budget left
Budget Utilization
85.5%Spent
₹358 Cr
Remaining
₹61 Cr
Total
₹419 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/02/2020
Revised Completion
15/03/2024
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹419 Cr — no cost escalation recorded.
Expenditure stands at ₹358 Cr, which is 85.5% of the revised project cost.
Remaining budget: ₹61 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 Augustmuni to Kund & Guptkashi to Sitapur on NH 109 in UK is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹419.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to "?
- Construction & Widening Including Augustmuni Bypass Ch-16.545 to Ch - 19.890 to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 Augustmuni to Kund & Guptkashi to Sitapur on NH 109 in UK is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹419 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹419 Cr has not been significantly revised. Expenditure: ₹358 Cr (85.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction & Widening Including Augustmuni Bypass Ch-16.54 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617968. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction & Widening Including Augustmuni Bypass Ch-16.54 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.