Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Construction & Upgradation to 2-lane with paved sh
Roads & HighwaysIPM · Central Project#618400

Construction & Upgradation to 2-lane with paved shoulder from Design Km 67.805 at the end of Km 83rd Tunnel near Dhrabshalla Ex. Km 83905 to Km 80.675 start of Kishtwar Bypass - Dulhasti Ex. Km 970751 of 12.870 Km length on chenani-Sudhmahadev-Goha Khellani-Kishtwar-vailoo-Donipawa-Ashajipora seition of NH-244 in the UT of J&K on EPC Mode under NHO-Gen Pkg-3

Ministry of Road Transport & HighwaysJammu & KashmirData: 2026-05
Revised Cost: ₹399 CrUtilization: 24.9%

Original Cost

₹399 Cr

Baseline estimate

On Budget

Revised Cost

₹399 Cr

Latest approved cost

Expenditure

₹99 Cr

Spent to date

Utilization

24.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹300 Cr

Budget left

Budget Utilization

24.9%
0%25%50%75%100%

Spent

₹99 Cr

Remaining

₹300 Cr

Total

₹399 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2022

Revised Completion

31/08/2025

Completed

Project Details

Project Code618400
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-05

Financial & Timeline

Original Cost₹399 Cr
Revised Cost₹399 Cr
Expenditure₹99 Cr
Original End Date31/12/2022
Revised Date31/08/2025

Project Intelligence

Project is within original budget of ₹399 Cr — no cost escalation recorded.

Expenditure stands at ₹99 Cr, which is 24.9% of the revised project cost.

Remaining budget: ₹300 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Frequently Asked Questions

What is IPM project "Construction & Upgradation to 2-lane with paved shoulder from Design Km 67.805 a"?
Construction & Upgradation to 2-lane with paved shoulder from Design Km 67.805 at the end of Km 83rd Tunnel near Dhrabshalla Ex. Km 83905 to Km 80.675 start of Kishtwar Bypass - Dulhasti Ex. Km 970751 of 12.870 Km length on chenani-Sudhmahadev-Goha Khellani-Kishtwar-vailoo-Donipawa-Ashajipora seition of NH-244 in the UT of J&K on EPC Mode under NHO-Gen Pkg-3 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹399 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost of ₹399 Cr has not been significantly revised. Expenditure: ₹99 Cr (24.9% of cost). Data as of 2026-05.
Which ministry is responsible for this project?
Construction & Upgradation to 2-lane with paved shoulder fro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618400. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction & Upgradation to 2-lane with paved shoulder fro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview