Original Cost
₹399 Cr
Baseline estimate
Revised Cost
₹399 Cr
Latest approved cost
Expenditure
₹99 Cr
Spent to date
Utilization
24.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹300 Cr
Budget left
Spent
₹99 Cr
Remaining
₹300 Cr
Total
₹399 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2022
Revised Completion
31/08/2025
Completed
Project is within original budget of ₹399 Cr — no cost escalation recorded.
Expenditure stands at ₹99 Cr, which is 24.9% of the revised project cost.
Remaining budget: ₹300 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.