Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of Kafer- Lava More section from km 40.00 to km 61.100 of NH717-A on EPC under SARDP-NE A in state of West Bengal Pkg-VA
Original Cost
₹311 Cr
Baseline estimate
Revised Cost
₹274 Cr
Latest approved cost
Expenditure
₹268 Cr
Spent to date
Utilization
98.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹6 Cr
Budget left
Budget Utilization
98.0%Spent
₹268 Cr
Remaining
₹6 Cr
Total
₹274 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
05/04/2023
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹311 Cr — no cost escalation recorded.
Expenditure stands at ₹268 Cr, which is 98.0% of the revised project cost.
Remaining budget: ₹6 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of Kafer- Lava More section from km 40.00 to km 61.100 of NH717-A on EPC under SARDP-NE A in state of West Bengal Pkg-VA is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹311.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction & upgradation of existing road to 2-lane with paved shoulder includ"?
- Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of Kafer- Lava More section from km 40.00 to km 61.100 of NH717-A on EPC under SARDP-NE A in state of West Bengal Pkg-VA is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: West Bengal. Original cost: ₹311 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹311 Cr and has been revised to ₹274 Cr — a cost overrun of -12%. Expenditure to date: ₹268 Cr (98.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction & upgradation of existing road to 2-lane with p is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618427. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction & upgradation of existing road to 2-lane with p is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.