Construction & Upgradation of existing road to 2-lane with paved shoulder from New Rolep Bridge at km 37.600 to Chochenpheri at km 52.00 in the section of Rongli to Chochenpheri of NH 717B Pkg-II C
Original Cost
₹493 Cr
Baseline estimate
Revised Cost
₹479 Cr
Latest approved cost
Expenditure
₹395 Cr
Spent to date
Utilization
82.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹84 Cr
Budget left
Budget Utilization
82.5%Spent
₹395 Cr
Remaining
₹84 Cr
Total
₹479 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
23/05/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹493 Cr — no cost escalation recorded.
Expenditure stands at ₹395 Cr, which is 82.5% of the revised project cost.
Remaining budget: ₹84 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction & Upgradation of existing road to 2-lane with paved shoulder from New Rolep Bridge at km 37.600 to Chochenpheri at km 52.00 in the section of Rongli to Chochenpheri of NH 717B Pkg-II C is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹493.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction & Upgradation of existing road to 2-lane with paved shoulder from N"?
- Construction & Upgradation of existing road to 2-lane with paved shoulder from New Rolep Bridge at km 37.600 to Chochenpheri at km 52.00 in the section of Rongli to Chochenpheri of NH 717B Pkg-II C is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Sikkim. Original cost: ₹493 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹493 Cr and has been revised to ₹479 Cr — a cost overrun of -2.9%. Expenditure to date: ₹395 Cr (82.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction & Upgradation of existing road to 2-lane with p is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618446. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction & Upgradation of existing road to 2-lane with p is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.