Original Cost
₹230 Cr
Baseline estimate
Revised Cost
₹245 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+6.5%
+₹15 Cr increase
Remaining
₹245 Cr
Budget left
Spent
₹0 Cr
Remaining
₹245 Cr
Total
₹245 Cr
Original Cost
₹230 Cr
Revised Cost
₹245 Cr
Increase
+₹15 Cr
Escalation
+6.5%
Project Approved
Construction / Implementation
Original End Date
15/04/2023
Revised Completion
30/09/2026
Completed
Cost has increased by ₹15 Cr (6.5%) from the original estimate of ₹230 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹245 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.