Construction & Upgradation of existing road to 2-lane with paved shoulder from km27.200 End of Rongli bypass to km37.600New Rolep Bridge of Rhenok-Menla spur NH-717B on EPC Mode under SARDP-NE Phase-A in Sikkim Pkg-II B
Original Cost
₹230 Cr
Baseline estimate
Revised Cost
₹245 Cr
Latest approved cost
Expenditure
₹250 Cr
Spent to date
Utilization
102.0%
Of revised budget
Cost Status
+6.5%
+₹15 Cr increase
Remaining
₹0 Cr
Budget left
Budget Utilization
102.0%Spent
₹250 Cr
Remaining
₹0 Cr
Total
₹245 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹230 Cr
Revised Cost
₹245 Cr
Increase
+₹15 Cr
Escalation
+6.5%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
15/04/2023
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹15 Cr (6.5%) from the original estimate of ₹230 Cr.
Expenditure stands at ₹250 Cr, which is 102.0% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction & Upgradation of existing road to 2-lane with paved shoulder from km27.200 End of Rongli bypass to km37.600New Rolep Bridge of Rhenok-Menla spur NH-717B on EPC Mode under SARDP-NE Phase-A in Sikkim Pkg-II B is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹230.00 Cr, later revised to ₹244.91 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction & Upgradation of existing road to 2-lane with paved shoulder from k"?
- Construction & Upgradation of existing road to 2-lane with paved shoulder from km27.200 End of Rongli bypass to km37.600New Rolep Bridge of Rhenok-Menla spur NH-717B on EPC Mode under SARDP-NE Phase-A in Sikkim Pkg-II B is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Sikkim. Original cost: ₹230 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹230 Cr and has been revised to ₹245 Cr — a cost overrun of +6.5%. Expenditure to date: ₹250 Cr (102.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction & Upgradation of existing road to 2-lane with p is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618449. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction & Upgradation of existing road to 2-lane with p is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.