Original Cost
₹640 Cr
Baseline estimate
Revised Cost
₹603 Cr
Latest approved cost
Expenditure
₹239 Cr
Spent to date
Utilization
39.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹364 Cr
Budget left
Spent
₹239 Cr
Remaining
₹364 Cr
Total
₹603 Cr
Project Approved
Construction / Implementation
Original End Date
29/11/2025
Revised Completion
31/07/2026
Completed
Project is within original budget of ₹640 Cr — no cost escalation recorded.
Expenditure stands at ₹239 Cr, which is 39.7% of the revised project cost.
Remaining budget: ₹364 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.