Construction of two lane with paved shoulder Gangtok Bypass Road from Ranipool to Burtuk Ch 0.00 Km to 23.316 L23.316 Km in the State of Sikkim
Original Cost
₹385 Cr
Baseline estimate
Revised Cost
₹343 Cr
Latest approved cost
Expenditure
₹255 Cr
Spent to date
Utilization
74.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹88 Cr
Budget left
Budget Utilization
74.2%Spent
₹255 Cr
Remaining
₹88 Cr
Total
₹343 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
22/05/2024
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹385 Cr — no cost escalation recorded.
Expenditure stands at ₹255 Cr, which is 74.2% of the revised project cost.
Remaining budget: ₹88 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of two lane with paved shoulder Gangtok Bypass Road from Ranipool to Burtuk Ch 0.00 Km to 23.316 L23.316 Km in the State of Sikkim is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹385.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of two lane with paved shoulder Gangtok Bypass Road from Ranipool t"?
- Construction of two lane with paved shoulder Gangtok Bypass Road from Ranipool to Burtuk Ch 0.00 Km to 23.316 L23.316 Km in the State of Sikkim is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Sikkim. Original cost: ₹385 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹385 Cr and has been revised to ₹343 Cr — a cost overrun of -10.9%. Expenditure to date: ₹255 Cr (74.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of two lane with paved shoulder Gangtok Bypass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618071. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of two lane with paved shoulder Gangtok Bypass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.