Roads & HighwaysIPM · Central Project#618535

Construction of Six lane elevated flyover including reconstruction/rehabilitation of existing pavement from Km 406100 to Km 411150 Length 5.05 Km at Gobindpur area in the Barwa Adda Panagarh section of NH-19 from Km.398.240 to Km.521.120 including Panagarh Bypass in the State of Jharkhand on EPC Mode.

Ministry of Road Transport & HighwaysJharkhand
Revised Cost: ₹443 CrUtilization: 18.2%

Original Cost

₹688 Cr

Baseline estimate

On budget

Revised Cost

₹443 Cr

Latest approved cost

Expenditure

₹81 Cr

Spent to date

Utilization

18.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹362 Cr

Budget left

Budget Utilization

18.2%
0%25%50%75%100%

Spent

₹81 Cr

Remaining

₹362 Cr

Total

₹443 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

21/03/2028

Revised Completion

21/03/2028

Completed

Project Details

Project Code618535
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹688 Cr
Revised Cost₹443 Cr
Expenditure₹81 Cr
Original End Date21/03/2028
Revised Date21/03/2028

Project Intelligence

Project is within original budget of ₹688 Cr — no cost escalation recorded.

Expenditure stands at ₹81 Cr, which is 18.2% of the revised project cost.

Remaining budget: ₹362 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Six lane elevated flyover including reconstruction/rehabilitation of existing pavement from Km 406100 to Km 411150 Length 5.05 Km at Gobindpur area in the Barwa Adda Panagarh section of NH-19 from Km.398.240 to Km.521.120 including Panagarh Bypass in the State of Jharkhand on EPC Mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹688.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Six lane elevated flyover including reconstruction/rehabilitatio"?
Construction of Six lane elevated flyover including reconstruction/rehabilitation of existing pavement from Km 406100 to Km 411150 Length 5.05 Km at Gobindpur area in the Barwa Adda Panagarh section of NH-19 from Km.398.240 to Km.521.120 including Panagarh Bypass in the State of Jharkhand on EPC Mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹688 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹688 Cr and has been revised to ₹443 Cr — a cost overrun of -35.7%. Expenditure to date: ₹81 Cr (18.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Six lane elevated flyover including reconstr is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618535. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Six lane elevated flyover including reconstr is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.