Original Cost
₹688 Cr
Baseline estimate
Revised Cost
₹443 Cr
Latest approved cost
Expenditure
₹48 Cr
Spent to date
Utilization
10.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹395 Cr
Budget left
Spent
₹48 Cr
Remaining
₹395 Cr
Total
₹443 Cr
Project Approved
Construction / Implementation
Original End Date
21/03/2028
Revised Completion
21/03/2028
Completed
Project is within original budget of ₹688 Cr — no cost escalation recorded.
Expenditure stands at ₹48 Cr, which is 10.8% of the revised project cost.
Remaining budget: ₹395 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.