Roads & HighwaysIPM · Central Project#617980

Construction of six lane elevated corridor from km 7.950 Uppal to km 14.200 of NH-163 to De-Congest the urban limits of Hyderabad-Bhoopalapatnam section on EPC mode in the state of Telangana

Ministry of Road Transport & HighwaysTelangana
Revised Cost: ₹627 CrUtilization: 46.4%

Original Cost

₹627 Cr

Baseline estimate

On budget

Revised Cost

₹627 Cr

Latest approved cost

Expenditure

₹291 Cr

Spent to date

Utilization

46.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹336 Cr

Budget left

Budget Utilization

46.4%
0%25%50%75%100%

Spent

₹291 Cr

Remaining

₹336 Cr

Total

₹627 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/07/2020

Revised Completion

31/12/2027

Completed

Project Details

Project Code617980
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹627 Cr
Revised Cost₹627 Cr
Expenditure₹291 Cr
Original End Date01/07/2020
Revised Date31/12/2027

Project Intelligence

Project is within original budget of ₹627 Cr — no cost escalation recorded.

Expenditure stands at ₹291 Cr, which is 46.4% of the revised project cost.

Remaining budget: ₹336 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of six lane elevated corridor from km 7.950 Uppal to km 14.200 of NH-163 to De-Congest the urban limits of Hyderabad-Bhoopalapatnam section on EPC mode in the state of Telangana is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹627.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of six lane elevated corridor from km 7.950 Uppal to km 14.200 of "?
Construction of six lane elevated corridor from km 7.950 Uppal to km 14.200 of NH-163 to De-Congest the urban limits of Hyderabad-Bhoopalapatnam section on EPC mode in the state of Telangana is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹627 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹627 Cr has not been significantly revised. Expenditure: ₹291 Cr (46.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of six lane elevated corridor from km 7.950 Up is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617980. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of six lane elevated corridor from km 7.950 Up is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.