Construction of road from Bomdilla 9th Mile - Nafra Lada section of Frontier Highway NH-913 Package 4 Dishum-Sachung-Lada 113.00 to 167.75 54.75km
Original Cost
₹1267 Cr
Baseline estimate
Revised Cost
₹1267 Cr
Latest approved cost
Expenditure
₹108 Cr
Spent to date
Utilization
8.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1159 Cr
Budget left
Budget Utilization
8.5%Spent
₹108 Cr
Remaining
₹1159 Cr
Total
₹1267 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/07/2030
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1267 Cr — no cost escalation recorded.
Expenditure stands at ₹108 Cr, which is 8.5% of the revised project cost.
Remaining budget: ₹1159 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of road from Bomdilla 9th Mile - Nafra Lada section of Frontier Highway NH-913 Package 4 Dishum-Sachung-Lada 113.00 to 167.75 54.75km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1267.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of road from Bomdilla 9th Mile - Nafra Lada section of Frontier "?
- Construction of road from Bomdilla 9th Mile - Nafra Lada section of Frontier Highway NH-913 Package 4 Dishum-Sachung-Lada 113.00 to 167.75 54.75km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Arunachal Pradesh. Original cost: ₹1267 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1267 Cr has not been significantly revised. Expenditure: ₹108 Cr (8.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of road from Bomdilla 9th Mile - Nafra Lada is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619256. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of road from Bomdilla 9th Mile - Nafra Lada is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.