Construction of Ring Road around Kanpur from Ch.23.325 to Ch.32.090 Chaudhariya to Transganga Package-IIA
Original Cost
₹1089 Cr
Baseline estimate
Revised Cost
₹977 Cr
Latest approved cost
Expenditure
₹260 Cr
Spent to date
Utilization
26.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹717 Cr
Budget left
Budget Utilization
26.6%Spent
₹260 Cr
Remaining
₹717 Cr
Total
₹977 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/10/2027
Revised Completion
29/04/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1089 Cr — no cost escalation recorded.
Expenditure stands at ₹260 Cr, which is 26.6% of the revised project cost.
Remaining budget: ₹717 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Ring Road around Kanpur from Ch.23.325 to Ch.32.090 Chaudhariya to Transganga Package-IIA is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1089.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Ring Road around Kanpur from Ch.23.325 to Ch.32.090 Chaudhariya"?
- Construction of Ring Road around Kanpur from Ch.23.325 to Ch.32.090 Chaudhariya to Transganga Package-IIA is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1089 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1089 Cr and has been revised to ₹977 Cr — a cost overrun of -10.2%. Expenditure to date: ₹260 Cr (26.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Ring Road around Kanpur from Ch.23.325 to C is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618540. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Ring Road around Kanpur from Ch.23.325 to C is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.