Roads & HighwaysIPM · Central Project#618204

Construction of realignment between Pandrass- Pashkyun Total length 27.10 km on road Zozila-Kargil -Leh NH-1 to 2 lane specifications i.e. Drass alignment 9.30 km Kharboo realignment 6.30 km & Kargil alignment 11.50 km under project Vijayak BRO in the UT of Ladakh on EPC Mode

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹426 CrUtilization: 27.9%

Original Cost

₹426 Cr

Baseline estimate

On budget

Revised Cost

₹426 Cr

Latest approved cost

Expenditure

₹119 Cr

Spent to date

Utilization

27.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹307 Cr

Budget left

Budget Utilization

27.9%
0%25%50%75%100%

Spent

₹119 Cr

Remaining

₹307 Cr

Total

₹426 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

18/06/2025

Revised Completion

31/07/2027

Completed

Project Details

Project Code618204
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹426 Cr
Revised Cost₹426 Cr
Expenditure₹119 Cr
Original End Date18/06/2025
Revised Date31/07/2027

Project Intelligence

Project is within original budget of ₹426 Cr — no cost escalation recorded.

Expenditure stands at ₹119 Cr, which is 27.9% of the revised project cost.

Remaining budget: ₹307 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of realignment between Pandrass- Pashkyun Total length 27.10 km on road Zozila-Kargil -Leh NH-1 to 2 lane specifications i.e. Drass alignment 9.30 km Kharboo realignment 6.30 km & Kargil alignment 11.50 km under project Vijayak BRO in the UT of Ladakh on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹426.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of realignment between Pandrass- Pashkyun Total length 27.10 km "?
Construction of realignment between Pandrass- Pashkyun Total length 27.10 km on road Zozila-Kargil -Leh NH-1 to 2 lane specifications i.e. Drass alignment 9.30 km Kharboo realignment 6.30 km & Kargil alignment 11.50 km under project Vijayak BRO in the UT of Ladakh on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹426 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹426 Cr has not been significantly revised. Expenditure: ₹119 Cr (27.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of realignment between Pandrass- Pashkyun Tot is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618204. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of realignment between Pandrass- Pashkyun Tot is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.