Construction of New Double Tier 4L Elevated Corridor from Chennai Port to Maduravoyal in Chennai District from km -0.342 to Km 20.593 and Package II from Km 4.604 to Km 9.700
Original Cost
₹1617 Cr
Baseline estimate
Revised Cost
₹1617 Cr
Latest approved cost
Expenditure
₹271 Cr
Spent to date
Utilization
16.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1346 Cr
Budget left
Budget Utilization
16.8%Spent
₹271 Cr
Remaining
₹1346 Cr
Total
₹1617 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/05/2026
Revised Completion
31/03/2029
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1617 Cr — no cost escalation recorded.
Expenditure stands at ₹271 Cr, which is 16.8% of the revised project cost.
Remaining budget: ₹1346 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of New Double Tier 4L Elevated Corridor from Chennai Port to Maduravoyal in Chennai District from km -0.342 to Km 20.593 and Package II from Km 4.604 to Km 9.700 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1617.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of New Double Tier 4L Elevated Corridor from Chennai Port to Madura"?
- Construction of New Double Tier 4L Elevated Corridor from Chennai Port to Maduravoyal in Chennai District from km -0.342 to Km 20.593 and Package II from Km 4.604 to Km 9.700 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹1617 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1617 Cr has not been significantly revised. Expenditure: ₹271 Cr (16.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of New Double Tier 4L Elevated Corridor from Ch is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618800. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of New Double Tier 4L Elevated Corridor from Ch is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.