Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Construction of New Double Tier 4-lane Elevated Co
Roads & HighwaysIPM · Central Project#618801

Construction of New Double Tier 4-lane Elevated Corridor from Chennai Port to Maduravoyal in Chennai District from Km -0342 to Km 20223 Package 1 from Km -0342 to Km 4604

Ministry of Road Transport & HighwaysTamil NaduData: 2026-05
Revised Cost: ₹1389 CrUtilization: 15.1%

Original Cost

₹1389 Cr

Baseline estimate

On Budget

Revised Cost

₹1389 Cr

Latest approved cost

Expenditure

₹209 Cr

Spent to date

Utilization

15.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1179 Cr

Budget left

Budget Utilization

15.1%
0%25%50%75%100%

Spent

₹209 Cr

Remaining

₹1179 Cr

Total

₹1389 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/05/2026

Revised Completion

31/03/2029

Completed

Project Details

Project Code618801
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTamil Nadu
Data Month2026-05

Financial & Timeline

Original Cost₹1389 Cr
Revised Cost₹1389 Cr
Expenditure₹209 Cr
Original End Date20/05/2026
Revised Date31/03/2029

Project Intelligence

Project is within original budget of ₹1389 Cr — no cost escalation recorded.

Expenditure stands at ₹209 Cr, which is 15.1% of the revised project cost.

Remaining budget: ₹1179 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Frequently Asked Questions

What is IPM project "Construction of New Double Tier 4-lane Elevated Corridor from Chennai Port to Ma"?
Construction of New Double Tier 4-lane Elevated Corridor from Chennai Port to Maduravoyal in Chennai District from Km -0342 to Km 20223 Package 1 from Km -0342 to Km 4604 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹1389 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost of ₹1389 Cr has not been significantly revised. Expenditure: ₹209 Cr (15.1% of cost). Data as of 2026-05.
Which ministry is responsible for this project?
Construction of New Double Tier 4-lane Elevated Corridor fro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618801. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of New Double Tier 4-lane Elevated Corridor fro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview