Roads & HighwaysIPM · Central Project#618956

Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹380 CrUtilization: 15.2%

Original Cost

₹499 Cr

Baseline estimate

On budget

Revised Cost

₹380 Cr

Latest approved cost

Expenditure

₹58 Cr

Spent to date

Utilization

15.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹323 Cr

Budget left

Budget Utilization

15.2%
0%25%50%75%100%

Spent

₹58 Cr

Remaining

₹323 Cr

Total

₹380 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/04/2027

Revised Completion

16/03/2028

Completed

Project Details

Project Code618956
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹499 Cr
Revised Cost₹380 Cr
Expenditure₹58 Cr
Original End Date30/04/2027
Revised Date16/03/2028

Project Intelligence

Project is within original budget of ₹499 Cr — no cost escalation recorded.

Expenditure stands at ₹58 Cr, which is 15.2% of the revised project cost.

Remaining budget: ₹323 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹499.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Major Bridge over Baghmati and Lakhandei River along with Approa"?
Construction of Major Bridge over Baghmati and Lakhandei River along with Approaches from Design km.16.500 to km.21.500 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹499 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹499 Cr and has been revised to ₹380 Cr — a cost overrun of -23.8%. Expenditure to date: ₹58 Cr (15.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Major Bridge over Baghmati and Lakhandei Riv is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618956. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Major Bridge over Baghmati and Lakhandei Riv is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.