Original Cost
₹157 Cr
Baseline estimate
Revised Cost
₹188 Cr
Latest approved cost
Expenditure
₹103 Cr
Spent to date
Utilization
55.1%
Of revised budget
Cost Status
+19.5%
+₹31 Cr increase
Remaining
₹84 Cr
Budget left
Spent
₹103 Cr
Remaining
₹84 Cr
Total
₹188 Cr
Original Cost
₹157 Cr
Revised Cost
₹188 Cr
Increase
+₹31 Cr
Escalation
+19.5%
Project Approved
Construction / Implementation
Original End Date
06/11/2021
Revised Completion
30/04/2027
Completed
Cost has increased by ₹31 Cr (19.5%) from the original estimate of ₹157 Cr.
Expenditure stands at ₹103 Cr, which is 55.1% of the revised project cost.
Remaining budget: ₹84 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.