Construction of left out portion of Agra Inner Ring Road connecting village Deori to NH-44 village Bad from Km. 0.000 to Km. 7.772
Original Cost
₹879 Cr
Baseline estimate
Revised Cost
₹788 Cr
Latest approved cost
Expenditure
₹629 Cr
Spent to date
Utilization
79.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹158 Cr
Budget left
Budget Utilization
79.9%Spent
₹629 Cr
Remaining
₹158 Cr
Total
₹788 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/09/2024
Revised Completion
30/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹879 Cr — no cost escalation recorded.
Expenditure stands at ₹629 Cr, which is 79.9% of the revised project cost.
Remaining budget: ₹158 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of left out portion of Agra Inner Ring Road connecting village Deori to NH-44 village Bad from Km. 0.000 to Km. 7.772 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹879.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of left out portion of Agra Inner Ring Road connecting village Deor"?
- Construction of left out portion of Agra Inner Ring Road connecting village Deori to NH-44 village Bad from Km. 0.000 to Km. 7.772 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹879 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹879 Cr and has been revised to ₹788 Cr — a cost overrun of -10.4%. Expenditure to date: ₹629 Cr (79.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of left out portion of Agra Inner Ring Road con is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618554. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of left out portion of Agra Inner Ring Road con is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.