Original Cost
₹154 Cr
Baseline estimate
Revised Cost
₹154 Cr
Latest approved cost
Expenditure
₹22 Cr
Spent to date
Utilization
14.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹132 Cr
Budget left
Spent
₹22 Cr
Remaining
₹132 Cr
Total
₹154 Cr
Project Approved
Construction / Implementation
Original End Date
26/12/2024
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹154 Cr — no cost escalation recorded.
Expenditure stands at ₹22 Cr, which is 14.5% of the revised project cost.
Remaining budget: ₹132 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.