Construction of four lane ROB and its approaches in lieu of existing Level Crossing No. RV-71 at km 435 on NH-217 New NH-353 at Khariar including land acquisition under NHO in Annual Plan 2021-22 for the state of Odisha for F.Y. 2021-22 to F.Y 2033-34
Original Cost
₹154 Cr
Baseline estimate
Revised Cost
₹154 Cr
Latest approved cost
Expenditure
₹106 Cr
Spent to date
Utilization
68.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹48 Cr
Budget left
Budget Utilization
68.8%Spent
₹106 Cr
Remaining
₹48 Cr
Total
₹154 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
26/12/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹154 Cr — no cost escalation recorded.
Expenditure stands at ₹106 Cr, which is 68.8% of the revised project cost.
Remaining budget: ₹48 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of four lane ROB and its approaches in lieu of existing Level Crossing No. RV-71 at km 435 on NH-217 New NH-353 at Khariar including land acquisition under NHO in Annual Plan 2021-22 for the state of Odisha for F.Y. 2021-22 to F.Y 2033-34 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹154.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of four lane ROB and its approaches in lieu of existing Level Cross"?
- Construction of four lane ROB and its approaches in lieu of existing Level Crossing No. RV-71 at km 435 on NH-217 New NH-353 at Khariar including land acquisition under NHO in Annual Plan 2021-22 for the state of Odisha for F.Y. 2021-22 to F.Y 2033-34 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹154 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹154 Cr has not been significantly revised. Expenditure: ₹106 Cr (68.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of four lane ROB and its approaches in lieu of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618003. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of four lane ROB and its approaches in lieu of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.