Roads & HighwaysIPM · Central Project#618003

Construction of four lane ROB and its approaches in lieu of existing Level Crossing No. RV-71 at km 435 on NH-217 New NH-353 at Khariar including land acquisition under NHO in Annual Plan 2021-22 for the state of Odisha for F.Y. 2021-22 to F.Y 2033-34

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹154 CrUtilization: 68.8%

Original Cost

₹154 Cr

Baseline estimate

On budget

Revised Cost

₹154 Cr

Latest approved cost

Expenditure

₹106 Cr

Spent to date

Utilization

68.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹48 Cr

Budget left

Budget Utilization

68.8%
0%25%50%75%100%

Spent

₹106 Cr

Remaining

₹48 Cr

Total

₹154 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/12/2024

Revised Completion

30/09/2026

Completed

Project Details

Project Code618003
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹154 Cr
Revised Cost₹154 Cr
Expenditure₹106 Cr
Original End Date26/12/2024
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹154 Cr — no cost escalation recorded.

Expenditure stands at ₹106 Cr, which is 68.8% of the revised project cost.

Remaining budget: ₹48 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of four lane ROB and its approaches in lieu of existing Level Crossing No. RV-71 at km 435 on NH-217 New NH-353 at Khariar including land acquisition under NHO in Annual Plan 2021-22 for the state of Odisha for F.Y. 2021-22 to F.Y 2033-34 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹154.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of four lane ROB and its approaches in lieu of existing Level Cross"?
Construction of four lane ROB and its approaches in lieu of existing Level Crossing No. RV-71 at km 435 on NH-217 New NH-353 at Khariar including land acquisition under NHO in Annual Plan 2021-22 for the state of Odisha for F.Y. 2021-22 to F.Y 2033-34 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹154 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹154 Cr has not been significantly revised. Expenditure: ₹106 Cr (68.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of four lane ROB and its approaches in lieu of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618003. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of four lane ROB and its approaches in lieu of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.