Roads & HighwaysIPM · Central Project#619141

Construction of four lane access controlled highway from Chillakuru cross road to Turpu KanupurPart 1 of Package - II km 0.000 131.500 of NH - 16 to km 23.770 on New NH-516W including six lane flyover and approaches on NH-16 length km 1.050 and six lane access controlled from Turpu Kanupur to Port South Gate Part 2 of Package - II km 23.770 to km 35.015 on New NH-516W in the state of Andhra Pradesh on HAM Mode under Bharatmala Pariyojana Phase I

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹844 CrUtilization: 43.7%

Original Cost

₹864 Cr

Baseline estimate

On budget

Revised Cost

₹844 Cr

Latest approved cost

Expenditure

₹369 Cr

Spent to date

Utilization

43.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹475 Cr

Budget left

Budget Utilization

43.7%
0%25%50%75%100%

Spent

₹369 Cr

Remaining

₹475 Cr

Total

₹844 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/12/2025

Revised Completion

08/03/2026

Completed

Project Details

Project Code619141
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹864 Cr
Revised Cost₹844 Cr
Expenditure₹369 Cr
Original End Date06/12/2025
Revised Date08/03/2026

Project Intelligence

Project is within original budget of ₹864 Cr — no cost escalation recorded.

Expenditure stands at ₹369 Cr, which is 43.7% of the revised project cost.

Remaining budget: ₹475 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of four lane access controlled highway from Chillakuru cross road to Turpu KanupurPart 1 of Package - II km 0.000 131.500 of NH - 16 to km 23.770 on New NH-516W including six lane flyover and approaches on NH-16 length km 1.050 and six lane access controlled from Turpu Kanupur to Port South Gate Part 2 of Package - II km 23.770 to km 35.015 on New NH-516W in the state of Andhra Pradesh on HAM Mode under Bharatmala Pariyojana Phase I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹864.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of four lane access controlled highway from Chillakuru cross road t"?
Construction of four lane access controlled highway from Chillakuru cross road to Turpu KanupurPart 1 of Package - II km 0.000 131.500 of NH - 16 to km 23.770 on New NH-516W including six lane flyover and approaches on NH-16 length km 1.050 and six lane access controlled from Turpu Kanupur to Port South Gate Part 2 of Package - II km 23.770 to km 35.015 on New NH-516W in the state of Andhra Pradesh on HAM Mode under Bharatmala Pariyojana Phase I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹864 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹864 Cr and has been revised to ₹844 Cr — a cost overrun of -2.3%. Expenditure to date: ₹369 Cr (43.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of four lane access controlled highway from Chi is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619141. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of four lane access controlled highway from Chi is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.