Original Cost
₹431 Cr
Baseline estimate
Revised Cost
₹431 Cr
Latest approved cost
Expenditure
₹347 Cr
Spent to date
Utilization
80.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹84 Cr
Budget left
Spent
₹347 Cr
Remaining
₹84 Cr
Total
₹431 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2024
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹431 Cr — no cost escalation recorded.
Expenditure stands at ₹347 Cr, which is 80.5% of the revised project cost.
Remaining budget: ₹84 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.