Original Cost
₹298 Cr
Baseline estimate
Revised Cost
₹349 Cr
Latest approved cost
Expenditure
₹175 Cr
Spent to date
Utilization
50.1%
Of revised budget
Cost Status
+17.3%
+₹51 Cr increase
Remaining
₹174 Cr
Budget left
Spent
₹175 Cr
Remaining
₹174 Cr
Total
₹349 Cr
Original Cost
₹298 Cr
Revised Cost
₹349 Cr
Increase
+₹51 Cr
Escalation
+17.3%
Project Approved
Construction / Implementation
Original End Date
04/06/2024
Revised Completion
30/11/2026
Completed
Cost has increased by ₹51 Cr (17.3%) from the original estimate of ₹298 Cr.
Expenditure stands at ₹175 Cr, which is 50.1% of the revised project cost.
Remaining budget: ₹174 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.