Roads & HighwaysIPM · Central Project +17.3% overrun#617935

Construction of Elevated corridor from Km. 135.650 to 136.300 on 63, from Km. 249 to Km. 250.050 on old NH-4 and from Km. 192.910 to Km. 193.350 on NH-218 from decongestion of traffic in Ranichennamma circle in Hubli city in the state of Karnataka on EPC basis

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹349 CrUtilization: 75.0%Overrun: +₹51 Cr

Original Cost

₹298 Cr

Baseline estimate

+17% overrun

Revised Cost

₹349 Cr

Latest approved cost

Expenditure

₹262 Cr

Spent to date

Utilization

75.0%

Of revised budget

Escalated

Cost Status

+17.3%

+₹51 Cr increase

Remaining

₹87 Cr

Budget left

Budget Utilization

75.0%
0%25%50%75%100%

Spent

₹262 Cr

Remaining

₹87 Cr

Total

₹349 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹298 Cr

Revised Cost

₹349 Cr

Increase

+₹51 Cr

Escalation

+17.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/06/2024

Revised Completion

30/11/2026

Completed

Project Details

Project Code617935
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹298 Cr
Revised Cost₹349 Cr
Expenditure₹262 Cr
Original End Date04/06/2024
Revised Date30/11/2026

Project Intelligence

Cost has increased by ₹51 Cr (17.3%) from the original estimate of ₹298 Cr.

Expenditure stands at ₹262 Cr, which is 75.0% of the revised project cost.

Remaining budget: ₹87 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Elevated corridor from Km. 135.650 to 136.300 on 63, from Km. 249 to Km. 250.050 on old NH-4 and from Km. 192.910 to Km. 193.350 on NH-218 from decongestion of traffic in Ranichennamma circle in Hubli city in the state of Karnataka on EPC basis is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹298.00 Cr, later revised to ₹349.49 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Elevated corridor from Km. 135.650 to 136.300 on 63, from Km. 24"?
Construction of Elevated corridor from Km. 135.650 to 136.300 on 63, from Km. 249 to Km. 250.050 on old NH-4 and from Km. 192.910 to Km. 193.350 on NH-218 from decongestion of traffic in Ranichennamma circle in Hubli city in the state of Karnataka on EPC basis is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹298 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹298 Cr and has been revised to ₹349 Cr — a cost overrun of +17.3%. Expenditure to date: ₹262 Cr (75.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Elevated corridor from Km. 135.650 to 136.30 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617935. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Elevated corridor from Km. 135.650 to 136.30 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.