Roads & HighwaysIPM · Central Project#619271

Construction of Elevated Corridor at Kherwara Town on Udaipur Ratanpur Shamlaji Section of NH-48 in Udaipur District in the State of Rajasthan on EPC mode

Ministry of Road Transport & HighwaysRajasthan
Revised Cost: ₹364 CrUtilization: 0.1%

Original Cost

₹364 Cr

Baseline estimate

On budget

Revised Cost

₹364 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹364 Cr

Budget left

Budget Utilization

0.1%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹364 Cr

Total

₹364 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/01/2029

Revised Completion

08/01/2029

Completed

Project Details

Project Code619271
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateRajasthan
Data Month2026-08

Financial Summary

Original Cost₹364 Cr
Revised Cost₹364 Cr
Expenditure₹0 Cr
Original End Date08/01/2029
Revised Date08/01/2029

Project Intelligence

Project is within original budget of ₹364 Cr — no cost escalation recorded.

Expenditure stands at ₹0 Cr, which is 0.1% of the revised project cost.

Remaining budget: ₹364 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Elevated Corridor at Kherwara Town on Udaipur Ratanpur Shamlaji Section of NH-48 in Udaipur District in the State of Rajasthan on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹364.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Elevated Corridor at Kherwara Town on Udaipur Ratanpur Shamlaji "?
Construction of Elevated Corridor at Kherwara Town on Udaipur Ratanpur Shamlaji Section of NH-48 in Udaipur District in the State of Rajasthan on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Rajasthan. Original cost: ₹364 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹364 Cr has not been significantly revised. Expenditure: ₹0 Cr (0.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Elevated Corridor at Kherwara Town on Udaipu is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619271. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Elevated Corridor at Kherwara Town on Udaipu is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.