Construction of Deoria Bypass from existing Km. 27.140 to existing Km. 46.780 Design Km. 49.109 on NH727A Design length 21.969 Km. to four lane with paved shoulder configuration under Hybrid Annuity Mode HAM in the State of Uttar Pradesh
Original Cost
₹1735 Cr
Baseline estimate
Revised Cost
₹1735 Cr
Latest approved cost
Expenditure
₹483 Cr
Spent to date
Utilization
27.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1252 Cr
Budget left
Budget Utilization
27.8%Spent
₹483 Cr
Remaining
₹1252 Cr
Total
₹1735 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/07/2027
Revised Completion
31/07/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1735 Cr — no cost escalation recorded.
Expenditure stands at ₹483 Cr, which is 27.8% of the revised project cost.
Remaining budget: ₹1252 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Deoria Bypass from existing Km. 27.140 to existing Km. 46.780 Design Km. 49.109 on NH727A Design length 21.969 Km. to four lane with paved shoulder configuration under Hybrid Annuity Mode HAM in the State of Uttar Pradesh is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1735.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Deoria Bypass from existing Km. 27.140 to existing Km. 46.780 De"?
- Construction of Deoria Bypass from existing Km. 27.140 to existing Km. 46.780 Design Km. 49.109 on NH727A Design length 21.969 Km. to four lane with paved shoulder configuration under Hybrid Annuity Mode HAM in the State of Uttar Pradesh is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1735 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹1735 Cr has not been significantly revised. Expenditure: ₹483 Cr (27.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Deoria Bypass from existing Km. 27.140 to ex is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618262. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Deoria Bypass from existing Km. 27.140 to ex is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.