Construction of Champawat Bypass with two lane with paved shoulder configuration starting from existing chainage 121.700 to existing chainage 129.450 Design Length 9.847 of NH-125 in District-Champawat in the state of Uttrakhand on EPC mode.
Original Cost
₹221 Cr
Baseline estimate
Revised Cost
₹221 Cr
Latest approved cost
Expenditure
₹9 Cr
Spent to date
Utilization
3.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹212 Cr
Budget left
Budget Utilization
3.9%Spent
₹9 Cr
Remaining
₹212 Cr
Total
₹221 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2027
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹221 Cr — no cost escalation recorded.
Expenditure stands at ₹9 Cr, which is 3.9% of the revised project cost.
Remaining budget: ₹212 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Champawat Bypass with two lane with paved shoulder configuration starting from existing chainage 121.700 to existing chainage 129.450 Design Length 9.847 of NH-125 in District-Champawat in the state of Uttrakhand on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹221.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Champawat Bypass with two lane with paved shoulder configuration"?
- Construction of Champawat Bypass with two lane with paved shoulder configuration starting from existing chainage 121.700 to existing chainage 129.450 Design Length 9.847 of NH-125 in District-Champawat in the state of Uttrakhand on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹221 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹221 Cr has not been significantly revised. Expenditure: ₹9 Cr (3.9% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Champawat Bypass with two lane with paved sh is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617890. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Champawat Bypass with two lane with paved sh is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.