Roads & HighwaysIPM · Central Project +8.8% overrun#617962

Construction of Bypass to Madurai Achambathu Viratipathu in between km 6/850 10/382 of NH 49 Extn New NH 85 including Land Acquisition on Engineering, Procurement & Construction EPC basis Contract under NH O Annual Plan 2021-22 in the state of Tamil Nadu job No.NH-49 Extn New NH 85 - TN-2021-22-997

Ministry of Road Transport & HighwaysTamil Nadu
Revised Cost: ₹260 CrUtilization: 83.6%Overrun: +₹21 Cr

Original Cost

₹239 Cr

Baseline estimate

+9% overrun

Revised Cost

₹260 Cr

Latest approved cost

Expenditure

₹217 Cr

Spent to date

Utilization

83.6%

Of revised budget

Escalated

Cost Status

+8.8%

+₹21 Cr increase

Remaining

₹43 Cr

Budget left

Budget Utilization

83.6%
0%25%50%75%100%

Spent

₹217 Cr

Remaining

₹43 Cr

Total

₹260 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹239 Cr

Revised Cost

₹260 Cr

Increase

+₹21 Cr

Escalation

+8.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

23/08/2026

Revised Completion

31/10/2026

Completed

Project Details

Project Code617962
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTamil Nadu
Data Month2026-08

Financial Summary

Original Cost₹239 Cr
Revised Cost₹260 Cr
Expenditure₹217 Cr
Original End Date23/08/2026
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹21 Cr (8.8%) from the original estimate of ₹239 Cr.

Expenditure stands at ₹217 Cr, which is 83.6% of the revised project cost.

Remaining budget: ₹43 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Bypass to Madurai Achambathu Viratipathu in between km 6/850 10/382 of NH 49 Extn New NH 85 including Land Acquisition on Engineering, Procurement & Construction EPC basis Contract under NH O Annual Plan 2021-22 in the state of Tamil Nadu job No.NH-49 Extn New NH 85 - TN-2021-22-997 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹239.00 Cr, later revised to ₹260.07 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Bypass to Madurai Achambathu Viratipathu in between km 6/850 "?
Construction of Bypass to Madurai Achambathu Viratipathu in between km 6/850 10/382 of NH 49 Extn New NH 85 including Land Acquisition on Engineering, Procurement & Construction EPC basis Contract under NH O Annual Plan 2021-22 in the state of Tamil Nadu job No.NH-49 Extn New NH 85 - TN-2021-22-997 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹239 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹239 Cr and has been revised to ₹260 Cr — a cost overrun of +8.8%. Expenditure to date: ₹217 Cr (83.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Bypass to Madurai Achambathu Viratipathu i is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617962. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Bypass to Madurai Achambathu Viratipathu i is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.