- lane with Paved shoulder from Ch. 40460 Design Ch. 38650 to Ch. 46860 Design Ch. 45050 of NH-219 Total length-16.150 Kmunder EPC mode in the state of Bihar
Original Cost
₹180 Cr
Baseline estimate
Revised Cost
₹180 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹180 Cr
Budget left
Spent
₹0 Cr
Remaining
₹180 Cr
Total
₹180 Cr
0.0%
Utilized
Project Approved
Construction / Implementation
Original End Date
2026-07-03
Revised Completion
2027-04-30
Completed
Project is within original budget of ₹180 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹180 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.