Construction of Balance works of Major Bridge over Middle Strait Creek between Km.106.590 to km108.553 of NH-04 connecting South Andaman & Baratang Island in the Union Territory of Andaman & Nicobar Islands on EPC basis
Original Cost
₹263 Cr
Baseline estimate
Revised Cost
₹372 Cr
Latest approved cost
Expenditure
₹112 Cr
Spent to date
Utilization
30.2%
Of revised budget
Cost Status
+41.4%
+₹109 Cr increase
Remaining
₹260 Cr
Budget left
Budget Utilization
30.2%Spent
₹112 Cr
Remaining
₹260 Cr
Total
₹372 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹263 Cr
Revised Cost
₹372 Cr
Increase
+₹109 Cr
Escalation
+41.4%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
25/02/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹109 Cr (41.4%) from the original estimate of ₹263 Cr.
Expenditure stands at ₹112 Cr, which is 30.2% of the revised project cost.
Remaining budget: ₹260 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Balance works of Major Bridge over Middle Strait Creek between Km.106.590 to km108.553 of NH-04 connecting South Andaman & Baratang Island in the Union Territory of Andaman & Nicobar Islands on EPC basis is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹263.00 Cr, later revised to ₹371.88 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Balance works of Major Bridge over Middle Strait Creek between K"?
- Construction of Balance works of Major Bridge over Middle Strait Creek between Km.106.590 to km108.553 of NH-04 connecting South Andaman & Baratang Island in the Union Territory of Andaman & Nicobar Islands on EPC basis is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andaman & Nicobar. Original cost: ₹263 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹263 Cr and has been revised to ₹372 Cr — a cost overrun of +41.4%. Expenditure to date: ₹112 Cr (30.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Balance works of Major Bridge over Middle St is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619186. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balance works of Major Bridge over Middle St is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.