Roads & HighwaysIPM · Central Project +41.4% overrun#619186

Construction of Balance works of Major Bridge over Middle Strait Creek between Km.106.590 to km108.553 of NH-04 connecting South Andaman & Baratang Island in the Union Territory of Andaman & Nicobar Islands on EPC basis

Ministry of Road Transport & HighwaysAndaman & Nicobar
Revised Cost: ₹372 CrUtilization: 30.2%Overrun: +₹109 Cr

Original Cost

₹263 Cr

Baseline estimate

+41% overrun

Revised Cost

₹372 Cr

Latest approved cost

Expenditure

₹112 Cr

Spent to date

Utilization

30.2%

Of revised budget

Escalated

Cost Status

+41.4%

+₹109 Cr increase

Remaining

₹260 Cr

Budget left

Budget Utilization

30.2%
0%25%50%75%100%

Spent

₹112 Cr

Remaining

₹260 Cr

Total

₹372 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹263 Cr

Revised Cost

₹372 Cr

Increase

+₹109 Cr

Escalation

+41.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/02/2026

Revised Completion

31/12/2026

Completed

Project Details

Project Code619186
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndaman & Nicobar
Data Month2026-08

Financial Summary

Original Cost₹263 Cr
Revised Cost₹372 Cr
Expenditure₹112 Cr
Original End Date25/02/2026
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹109 Cr (41.4%) from the original estimate of ₹263 Cr.

Expenditure stands at ₹112 Cr, which is 30.2% of the revised project cost.

Remaining budget: ₹260 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Balance works of Major Bridge over Middle Strait Creek between Km.106.590 to km108.553 of NH-04 connecting South Andaman & Baratang Island in the Union Territory of Andaman & Nicobar Islands on EPC basis is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹263.00 Cr, later revised to ₹371.88 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Balance works of Major Bridge over Middle Strait Creek between K"?
Construction of Balance works of Major Bridge over Middle Strait Creek between Km.106.590 to km108.553 of NH-04 connecting South Andaman & Baratang Island in the Union Territory of Andaman & Nicobar Islands on EPC basis is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andaman & Nicobar. Original cost: ₹263 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹263 Cr and has been revised to ₹372 Cr — a cost overrun of +41.4%. Expenditure to date: ₹112 Cr (30.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Balance works of Major Bridge over Middle St is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619186. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balance works of Major Bridge over Middle St is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.