Original Cost
₹263 Cr
Baseline estimate
Revised Cost
₹372 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+41.4%
+₹109 Cr increase
Remaining
₹372 Cr
Budget left
Spent
₹0 Cr
Remaining
₹372 Cr
Total
₹372 Cr
Original Cost
₹263 Cr
Revised Cost
₹372 Cr
Increase
+₹109 Cr
Escalation
+41.4%
Project Approved
Construction / Implementation
Original End Date
25/02/2026
Revised Completion
31/12/2026
Completed
Cost has increased by ₹109 Cr (41.4%) from the original estimate of ₹263 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹372 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.