in the State of Uttar Pradesh and Bihar on Hybrid Annuity Mode
Original Cost
₹532 Cr
Baseline estimate
Revised Cost
₹445 Cr
Latest approved cost
Expenditure
₹19 Cr
Spent to date
Utilization
4.2%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹426 Cr
Budget left
Spent
₹19 Cr
Remaining
₹426 Cr
Total
₹445 Cr
4.2%
Utilized
Project Approved
Construction / Implementation
Original End Date
2028-02-19
Revised Completion
2028-02-19
Completed
Project is within original budget of ₹532 Cr — no cost escalation recorded.
Expenditure stands at ₹19 Cr, which is 4.2% of the revised project cost.
Remaining budget: ₹426 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.