Original Cost
₹258 Cr
Baseline estimate
Revised Cost
₹193 Cr
Latest approved cost
Expenditure
₹47 Cr
Spent to date
Utilization
24.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹146 Cr
Budget left
Spent
₹47 Cr
Remaining
₹146 Cr
Total
₹193 Cr
Project Approved
Construction / Implementation
Original End Date
20/03/2027
Revised Completion
31/08/2027
Completed
Project is within original budget of ₹258 Cr — no cost escalation recorded.
Expenditure stands at ₹47 Cr, which is 24.1% of the revised project cost.
Remaining budget: ₹146 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.