Roads & HighwaysIPM · Central Project#618329

Construction of 4/6 Laning from Km 132.375 to Km 153.058 Total New Alignment length of 20.683 Km of Daboka-Dimapur Section Dimapur Bypass Nagaland Portion of NH-36 & 39 in the State of Nagaland on EPC basis under PhaseA of SARDP-NE

Ministry of Road Transport & HighwaysNagaland
Revised Cost: ₹819 CrUtilization: 0.0%

Original Cost

₹819 Cr

Baseline estimate

On budget

Revised Cost

₹819 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹819 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹819 Cr

Total

₹819 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/09/2020

Revised Completion

28/02/2023

Completed

Project Details

Project Code618329
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateNagaland
Data Month2026-05

Financial Summary

Original Cost₹819 Cr
Revised Cost₹819 Cr
Expenditure₹0 Cr
Original End Date04/09/2020
Revised Date28/02/2023

Project Intelligence

Project is within original budget of ₹819 Cr — no cost escalation recorded.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹819 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 4/6 Laning from Km 132.375 to Km 153.058 Total New Alignment length of 20.683 Km of Daboka-Dimapur Section Dimapur Bypass Nagaland Portion of NH-36 & 39 in the State of Nagaland on EPC basis under PhaseA of SARDP-NE is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹819.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 4/6 Laning from Km 132.375 to Km 153.058 Total New Alignment len"?
Construction of 4/6 Laning from Km 132.375 to Km 153.058 Total New Alignment length of 20.683 Km of Daboka-Dimapur Section Dimapur Bypass Nagaland Portion of NH-36 & 39 in the State of Nagaland on EPC basis under PhaseA of SARDP-NE is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹819 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹819 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Construction of 4/6 Laning from Km 132.375 to Km 153.058 Tot is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618329. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4/6 Laning from Km 132.375 to Km 153.058 Tot is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.