Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] Total New Alignment length of 14.325 Km of Daboka -Dimapur Section Dimapur Bypass in the state of Assam under SARDP-NE 'Phase-A' on EPC mode Assam Portion
Original Cost
₹511 Cr
Baseline estimate
Revised Cost
₹511 Cr
Latest approved cost
Expenditure
₹647 Cr
Spent to date
Utilization
126.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Budget Utilization
126.7%Spent
₹647 Cr
Remaining
₹0 Cr
Total
₹511 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
25/11/2022
Revised Completion
30/09/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹511 Cr — no cost escalation recorded.
Expenditure stands at ₹647 Cr, which is 126.7% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] Total New Alignment length of 14.325 Km of Daboka -Dimapur Section Dimapur Bypass in the state of Assam under SARDP-NE 'Phase-A' on EPC mode Assam Portion is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹511.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102."?
- Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] Total New Alignment length of 14.325 Km of Daboka -Dimapur Section Dimapur Bypass in the state of Assam under SARDP-NE 'Phase-A' on EPC mode Assam Portion is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹511 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹511 Cr has not been significantly revised. Expenditure: ₹647 Cr (126.7% of cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Construction of 4/6 Laning from existing Km 159.400 of NH-36 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618330. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4/6 Laning from existing Km 159.400 of NH-36 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.