Roads & HighwaysIPM · Central Project#618330

Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] Total New Alignment length of 14.325 Km of Daboka -Dimapur Section Dimapur Bypass in the state of Assam under SARDP-NE 'Phase-A' on EPC mode Assam Portion

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹511 CrUtilization: 126.7%

Original Cost

₹511 Cr

Baseline estimate

On budget

Revised Cost

₹511 Cr

Latest approved cost

Expenditure

₹647 Cr

Spent to date

Utilization

126.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹0 Cr

Budget left

Budget Utilization

126.7%
0%25%50%75%100%

Spent

₹647 Cr

Remaining

₹0 Cr

Total

₹511 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/11/2022

Revised Completion

30/09/2025

Completed

Project Details

Project Code618330
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-05

Financial Summary

Original Cost₹511 Cr
Revised Cost₹511 Cr
Expenditure₹647 Cr
Original End Date25/11/2022
Revised Date30/09/2025

Project Intelligence

Project is within original budget of ₹511 Cr — no cost escalation recorded.

Expenditure stands at ₹647 Cr, which is 126.7% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] Total New Alignment length of 14.325 Km of Daboka -Dimapur Section Dimapur Bypass in the state of Assam under SARDP-NE 'Phase-A' on EPC mode Assam Portion is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹511.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102."?
Construction of 4/6 Laning from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] Total New Alignment length of 14.325 Km of Daboka -Dimapur Section Dimapur Bypass in the state of Assam under SARDP-NE 'Phase-A' on EPC mode Assam Portion is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹511 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹511 Cr has not been significantly revised. Expenditure: ₹647 Cr (126.7% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Construction of 4/6 Laning from existing Km 159.400 of NH-36 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618330. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4/6 Laning from existing Km 159.400 of NH-36 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.