Original Cost
₹980 Cr
Baseline estimate
Revised Cost
₹980 Cr
Latest approved cost
Expenditure
₹16 Cr
Spent to date
Utilization
1.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹964 Cr
Budget left
Spent
₹16 Cr
Remaining
₹964 Cr
Total
₹980 Cr
Project Approved
Construction / Implementation
Original End Date
31/07/2026
Revised Completion
28/02/2027
Completed
Project is within original budget of ₹980 Cr — no cost escalation recorded.
Expenditure stands at ₹16 Cr, which is 1.7% of the revised project cost.
Remaining budget: ₹964 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.