Construction of 4 Lane ROB and its approaches at the level crossing LC No 29 B of Km 29 Ekangarsarai at NH 110 New NH 33 & Railway Km 32.63 at Fatwa FUT Islampur IPR section in the state of Bihar on EPC mode.
Original Cost
₹201 Cr
Baseline estimate
Revised Cost
₹201 Cr
Latest approved cost
Expenditure
₹58 Cr
Spent to date
Utilization
28.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹143 Cr
Budget left
Budget Utilization
28.8%Spent
₹58 Cr
Remaining
₹143 Cr
Total
₹201 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/07/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹201 Cr — no cost escalation recorded.
Expenditure stands at ₹58 Cr, which is 28.8% of the revised project cost.
Remaining budget: ₹143 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of 4 Lane ROB and its approaches at the level crossing LC No 29 B of Km 29 Ekangarsarai at NH 110 New NH 33 & Railway Km 32.63 at Fatwa FUT Islampur IPR section in the state of Bihar on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹201.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 4 Lane ROB and its approaches at the level crossing LC No 29 B "?
- Construction of 4 Lane ROB and its approaches at the level crossing LC No 29 B of Km 29 Ekangarsarai at NH 110 New NH 33 & Railway Km 32.63 at Fatwa FUT Islampur IPR section in the state of Bihar on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹201 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹201 Cr has not been significantly revised. Expenditure: ₹58 Cr (28.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of 4 Lane ROB and its approaches at the level c is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617969. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4 Lane ROB and its approaches at the level c is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.