Roads & HighwaysIPM · Central Project +7.8% overrun#618308

Construction of 4-Lane Panchgram Bypass from Design Chainage km 15500 on NH-37 Old NH-53 at Kalinagar Pt.-I Village to Design Chainage km 27300 at crossing with NH-6 Old NH-44 Near Siddeswar Pt.-I Village on Silchar - Churaibari stretch in the State of Assam on EPC Mode under Bharatmala Pariyojana in Economic Corridors Silchar- Churaibari Package-2

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹729 CrUtilization: 49.1%Overrun: +₹53 Cr

Original Cost

₹676 Cr

Baseline estimate

+8% overrun

Revised Cost

₹729 Cr

Latest approved cost

Expenditure

₹358 Cr

Spent to date

Utilization

49.1%

Of revised budget

Escalated

Cost Status

+7.8%

+₹53 Cr increase

Remaining

₹371 Cr

Budget left

Budget Utilization

49.1%
0%25%50%75%100%

Spent

₹358 Cr

Remaining

₹371 Cr

Total

₹729 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹676 Cr

Revised Cost

₹729 Cr

Increase

+₹53 Cr

Escalation

+7.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

09/02/2027

Revised Completion

31/03/2027

Completed

Project Details

Project Code618308
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹676 Cr
Revised Cost₹729 Cr
Expenditure₹358 Cr
Original End Date09/02/2027
Revised Date31/03/2027

Project Intelligence

Cost has increased by ₹53 Cr (7.8%) from the original estimate of ₹676 Cr.

Expenditure stands at ₹358 Cr, which is 49.1% of the revised project cost.

Remaining budget: ₹371 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 4-Lane Panchgram Bypass from Design Chainage km 15500 on NH-37 Old NH-53 at Kalinagar Pt.-I Village to Design Chainage km 27300 at crossing with NH-6 Old NH-44 Near Siddeswar Pt.-I Village on Silchar - Churaibari stretch in the State of Assam on EPC Mode under Bharatmala Pariyojana in Economic Corridors Silchar- Churaibari Package-2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹676.00 Cr, later revised to ₹728.97 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 4-Lane Panchgram Bypass from Design Chainage km 15500 on NH-37 O"?
Construction of 4-Lane Panchgram Bypass from Design Chainage km 15500 on NH-37 Old NH-53 at Kalinagar Pt.-I Village to Design Chainage km 27300 at crossing with NH-6 Old NH-44 Near Siddeswar Pt.-I Village on Silchar - Churaibari stretch in the State of Assam on EPC Mode under Bharatmala Pariyojana in Economic Corridors Silchar- Churaibari Package-2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹676 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹676 Cr and has been revised to ₹729 Cr — a cost overrun of +7.8%. Expenditure to date: ₹358 Cr (49.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 4-Lane Panchgram Bypass from Design Chainage is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618308. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4-Lane Panchgram Bypass from Design Chainage is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.