Roads & HighwaysIPM · Central Project +9.2% overrun#619142

Construction of 4-lane connectivity to Banbasa ICP at India Nepal border from NH-09 old NH-125 Sitarganj-Tanakpur at Km 40.00 near Jagbuda bridge under Bharatmala Priyojana of NH-109D on EPC mode in the State of Uttarakhand

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹237 CrUtilization: 92.4%Overrun: +₹20 Cr

Original Cost

₹217 Cr

Baseline estimate

+9% overrun

Revised Cost

₹237 Cr

Latest approved cost

Expenditure

₹219 Cr

Spent to date

Utilization

92.4%

Of revised budget

Escalated

Cost Status

+9.2%

+₹20 Cr increase

Remaining

₹18 Cr

Budget left

Budget Utilization

92.4%
0%25%50%75%100%

Spent

₹219 Cr

Remaining

₹18 Cr

Total

₹237 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹217 Cr

Revised Cost

₹237 Cr

Increase

+₹20 Cr

Escalation

+9.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/09/2024

Revised Completion

11/04/2027

Completed

Project Details

Project Code619142
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹217 Cr
Revised Cost₹237 Cr
Expenditure₹219 Cr
Original End Date01/09/2024
Revised Date11/04/2027

Project Intelligence

Cost has increased by ₹20 Cr (9.2%) from the original estimate of ₹217 Cr.

Expenditure stands at ₹219 Cr, which is 92.4% of the revised project cost.

Remaining budget: ₹18 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 4-lane connectivity to Banbasa ICP at India Nepal border from NH-09 old NH-125 Sitarganj-Tanakpur at Km 40.00 near Jagbuda bridge under Bharatmala Priyojana of NH-109D on EPC mode in the State of Uttarakhand is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹217.00 Cr, later revised to ₹237.01 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 4-lane connectivity to Banbasa ICP at India Nepal border from NH"?
Construction of 4-lane connectivity to Banbasa ICP at India Nepal border from NH-09 old NH-125 Sitarganj-Tanakpur at Km 40.00 near Jagbuda bridge under Bharatmala Priyojana of NH-109D on EPC mode in the State of Uttarakhand is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹217 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹217 Cr and has been revised to ₹237 Cr — a cost overrun of +9.2%. Expenditure to date: ₹219 Cr (92.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 4-lane connectivity to Banbasa ICP at India is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619142. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4-lane connectivity to Banbasa ICP at India is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.