Roads & HighwaysIPM · Central Project#618373

Construction of 4-Lane Bridge including approaches over River Brahmaputra between Dhubri on North Bank,Assam and Phulbari on south Bank,Meghalaya on NH-127B under JICA ODA Loan assistance Phase-III

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹4997 CrUtilization: 62.7%

Original Cost

₹4997 Cr

Baseline estimate

On budget

Revised Cost

₹4997 Cr

Latest approved cost

Expenditure

₹3133 Cr

Spent to date

Utilization

62.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1864 Cr

Budget left

Budget Utilization

62.7%
0%25%50%75%100%

Spent

₹3133 Cr

Remaining

₹1864 Cr

Total

₹4997 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

12/09/2028

Revised Completion

12/09/2028

Completed

Project Details

Project Code618373
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹4997 Cr
Revised Cost₹4997 Cr
Expenditure₹3133 Cr
Original End Date12/09/2028
Revised Date12/09/2028

Project Intelligence

Project is within original budget of ₹4997 Cr — no cost escalation recorded.

Expenditure stands at ₹3133 Cr, which is 62.7% of the revised project cost.

Remaining budget: ₹1864 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 4-Lane Bridge including approaches over River Brahmaputra between Dhubri on North Bank,Assam and Phulbari on south Bank,Meghalaya on NH-127B under JICA ODA Loan assistance Phase-III is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹4997.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 4-Lane Bridge including approaches over River Brahmaputra betwee"?
Construction of 4-Lane Bridge including approaches over River Brahmaputra between Dhubri on North Bank,Assam and Phulbari on south Bank,Meghalaya on NH-127B under JICA ODA Loan assistance Phase-III is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹4997 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹4997 Cr has not been significantly revised. Expenditure: ₹3133 Cr (62.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 4-Lane Bridge including approaches over Rive is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618373. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4-Lane Bridge including approaches over Rive is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.