Original Cost
₹817 Cr
Baseline estimate
Revised Cost
₹787 Cr
Latest approved cost
Expenditure
₹32 Cr
Spent to date
Utilization
4.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹754 Cr
Budget left
Spent
₹32 Cr
Remaining
₹754 Cr
Total
₹787 Cr
Project Approved
Construction / Implementation
Original End Date
09/12/2023
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹817 Cr — no cost escalation recorded.
Expenditure stands at ₹32 Cr, which is 4.1% of the revised project cost.
Remaining budget: ₹754 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.