Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chainages of NH-766C complete Realignment of 13.76 km with 2 major Bridges across Sharavathi Backwaters on EPC mode under Annual Plan 2022-23 in the state of Karnataka NH-766C-KNT-2022-23 dated 14.10.2022
Original Cost
₹314 Cr
Baseline estimate
Revised Cost
₹314 Cr
Latest approved cost
Expenditure
₹185 Cr
Spent to date
Utilization
59.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹129 Cr
Budget left
Budget Utilization
59.0%Spent
₹185 Cr
Remaining
₹129 Cr
Total
₹314 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
12/02/2026
Revised Completion
21/12/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹314 Cr — no cost escalation recorded.
Expenditure stands at ₹185 Cr, which is 59.0% of the revised project cost.
Remaining budget: ₹129 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chainages of NH-766C complete Realignment of 13.76 km with 2 major Bridges across Sharavathi Backwaters on EPC mode under Annual Plan 2022-23 in the state of Karnataka NH-766C-KNT-2022-23 dated 14.10.2022 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹314.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chai"?
- Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chainages of NH-766C complete Realignment of 13.76 km with 2 major Bridges across Sharavathi Backwaters on EPC mode under Annual Plan 2022-23 in the state of Karnataka NH-766C-KNT-2022-23 dated 14.10.2022 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹314 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹314 Cr has not been significantly revised. Expenditure: ₹185 Cr (59.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of 2 Lane with paved shoulder from km 55.6 to k is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618184. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2 Lane with paved shoulder from km 55.6 to k is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.