Roads & HighwaysIPM · Central Project#618184

Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chainages of NH-766C complete Realignment of 13.76 km with 2 major Bridges across Sharavathi Backwaters on EPC mode under Annual Plan 2022-23 in the state of Karnataka NH-766C-KNT-2022-23 dated 14.10.2022

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹314 CrUtilization: 59.0%

Original Cost

₹314 Cr

Baseline estimate

On budget

Revised Cost

₹314 Cr

Latest approved cost

Expenditure

₹185 Cr

Spent to date

Utilization

59.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹129 Cr

Budget left

Budget Utilization

59.0%
0%25%50%75%100%

Spent

₹185 Cr

Remaining

₹129 Cr

Total

₹314 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

12/02/2026

Revised Completion

21/12/2027

Completed

Project Details

Project Code618184
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹314 Cr
Revised Cost₹314 Cr
Expenditure₹185 Cr
Original End Date12/02/2026
Revised Date21/12/2027

Project Intelligence

Project is within original budget of ₹314 Cr — no cost escalation recorded.

Expenditure stands at ₹185 Cr, which is 59.0% of the revised project cost.

Remaining budget: ₹129 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chainages of NH-766C complete Realignment of 13.76 km with 2 major Bridges across Sharavathi Backwaters on EPC mode under Annual Plan 2022-23 in the state of Karnataka NH-766C-KNT-2022-23 dated 14.10.2022 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹314.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chai"?
Construction of 2 Lane with paved shoulder from km 55.6 to km 90.7 existing chainages of NH-766C complete Realignment of 13.76 km with 2 major Bridges across Sharavathi Backwaters on EPC mode under Annual Plan 2022-23 in the state of Karnataka NH-766C-KNT-2022-23 dated 14.10.2022 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹314 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹314 Cr has not been significantly revised. Expenditure: ₹185 Cr (59.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 2 Lane with paved shoulder from km 55.6 to k is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618184. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2 Lane with paved shoulder from km 55.6 to k is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.