Original Cost
₹217 Cr
Baseline estimate
Revised Cost
₹217 Cr
Latest approved cost
Expenditure
₹108 Cr
Spent to date
Utilization
49.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹109 Cr
Budget left
Spent
₹108 Cr
Remaining
₹109 Cr
Total
₹217 Cr
Project Approved
Construction / Implementation
Original End Date
05/12/2025
Revised Completion
Completed
Project is within original budget of ₹217 Cr — no cost escalation recorded.
Expenditure stands at ₹108 Cr, which is 49.6% of the revised project cost.
Remaining budget: ₹109 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.