Roads & HighwaysIPM · Central Project#618289

Construction and up gradation to 4-Lane of existing two lane with paved shoulder from Hapachara to Tulungia road of NH-117 of existing Km 0.00 to km 14.050 and Design Km 0.000 to km 14.660 under BMP on EPC mode

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹225 CrUtilization: 93.3%

Original Cost

₹225 Cr

Baseline estimate

On budget

Revised Cost

₹225 Cr

Latest approved cost

Expenditure

₹210 Cr

Spent to date

Utilization

93.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹15 Cr

Budget left

Budget Utilization

93.3%
0%25%50%75%100%

Spent

₹210 Cr

Remaining

₹15 Cr

Total

₹225 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/12/2022

Revised Completion

31/03/2026

Completed

Project Details

Project Code618289
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹225 Cr
Revised Cost₹225 Cr
Expenditure₹210 Cr
Original End Date26/12/2022
Revised Date31/03/2026

Project Intelligence

Project is within original budget of ₹225 Cr — no cost escalation recorded.

Expenditure stands at ₹210 Cr, which is 93.3% of the revised project cost.

Remaining budget: ₹15 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction and up gradation to 4-Lane of existing two lane with paved shoulder from Hapachara to Tulungia road of NH-117 of existing Km 0.00 to km 14.050 and Design Km 0.000 to km 14.660 under BMP on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹225.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction and up gradation to 4-Lane of existing two lane with paved shoulder"?
Construction and up gradation to 4-Lane of existing two lane with paved shoulder from Hapachara to Tulungia road of NH-117 of existing Km 0.00 to km 14.050 and Design Km 0.000 to km 14.660 under BMP on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹225 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹225 Cr has not been significantly revised. Expenditure: ₹210 Cr (93.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction and up gradation to 4-Lane of existing two lane is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618289. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction and up gradation to 4-Lane of existing two lane is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.