Roads & HighwaysIPM · Central Project#619204

Capacity Augmentation in the stretch of Pimpri Sado Vadape section of NH848 Km. 460900 to Km. 537000 by Construction of Slip/Service Road on either side at various locations total length 25.140 Km LHSRHS, Flyover 2 x 25m at Borivali Junction Km. 528550 & LVUP 1 x 15m at Sherekarpada Km. 528800

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹372 CrUtilization: 0.4%

Original Cost

₹372 Cr

Baseline estimate

On budget

Revised Cost

₹372 Cr

Latest approved cost

Expenditure

₹2 Cr

Spent to date

Utilization

0.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹371 Cr

Budget left

Budget Utilization

0.4%
0%25%50%75%100%

Spent

₹2 Cr

Remaining

₹371 Cr

Total

₹372 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/10/2027

Revised Completion

27/10/2027

Completed

Project Details

Project Code619204
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹372 Cr
Revised Cost₹372 Cr
Expenditure₹2 Cr
Original End Date27/10/2027
Revised Date27/10/2027

Project Intelligence

Project is within original budget of ₹372 Cr — no cost escalation recorded.

Expenditure stands at ₹2 Cr, which is 0.4% of the revised project cost.

Remaining budget: ₹371 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Capacity Augmentation in the stretch of Pimpri Sado Vadape section of NH848 Km. 460900 to Km. 537000 by Construction of Slip/Service Road on either side at various locations total length 25.140 Km LHSRHS, Flyover 2 x 25m at Borivali Junction Km. 528550 & LVUP 1 x 15m at Sherekarpada Km. 528800 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹372.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Capacity Augmentation in the stretch of Pimpri Sado Vadape section of NH848 Km."?
Capacity Augmentation in the stretch of Pimpri Sado Vadape section of NH848 Km. 460900 to Km. 537000 by Construction of Slip/Service Road on either side at various locations total length 25.140 Km LHSRHS, Flyover 2 x 25m at Borivali Junction Km. 528550 & LVUP 1 x 15m at Sherekarpada Km. 528800 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹372 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹372 Cr has not been significantly revised. Expenditure: ₹2 Cr (0.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Capacity Augmentation in the stretch of Pimpri Sado Vadape is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619204. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Capacity Augmentation in the stretch of Pimpri Sado Vadape is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.