Original Cost
₹622 Cr
Baseline estimate
Revised Cost
₹646 Cr
Latest approved cost
Expenditure
₹367 Cr
Spent to date
Utilization
56.8%
Of revised budget
Cost Status
+3.9%
+₹24 Cr increase
Remaining
₹279 Cr
Budget left
Spent
₹367 Cr
Remaining
₹279 Cr
Total
₹646 Cr
Original Cost
₹622 Cr
Revised Cost
₹646 Cr
Increase
+₹24 Cr
Escalation
+3.9%
Project Approved
Construction / Implementation
Original End Date
18/12/2021
Revised Completion
30/09/2026
Completed
Cost has increased by ₹24 Cr (3.9%) from the original estimate of ₹622 Cr.
Expenditure stands at ₹367 Cr, which is 56.8% of the revised project cost.
Remaining budget: ₹279 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.