Original Cost
₹1345 Cr
Baseline estimate
Revised Cost
₹1293 Cr
Latest approved cost
Expenditure
₹786 Cr
Spent to date
Utilization
60.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹507 Cr
Budget left
Spent
₹786 Cr
Remaining
₹507 Cr
Total
₹1293 Cr
Project Approved
Construction / Implementation
Original End Date
27/07/2024
Revised Completion
31/07/2026
Completed
Project is within original budget of ₹1345 Cr — no cost escalation recorded.
Expenditure stands at ₹786 Cr, which is 60.8% of the revised project cost.
Remaining budget: ₹507 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.