Roads & HighwaysIPM · Central Project#618693

Bodhre - Dhule

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹1293 CrUtilization: 64.8%

Original Cost

₹1345 Cr

Baseline estimate

On budget

Revised Cost

₹1293 Cr

Latest approved cost

Expenditure

₹838 Cr

Spent to date

Utilization

64.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹455 Cr

Budget left

Budget Utilization

64.8%
0%25%50%75%100%

Spent

₹838 Cr

Remaining

₹455 Cr

Total

₹1293 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/07/2024

Revised Completion

31/10/2026

Completed

Project Details

Project Code618693
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹1345 Cr
Revised Cost₹1293 Cr
Expenditure₹838 Cr
Original End Date27/07/2024
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹1345 Cr — no cost escalation recorded.

Expenditure stands at ₹838 Cr, which is 64.8% of the revised project cost.

Remaining budget: ₹455 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Bodhre - Dhule is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1345.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Bodhre - Dhule"?
Bodhre - Dhule is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹1345 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1345 Cr and has been revised to ₹1293 Cr — a cost overrun of -3.9%. Expenditure to date: ₹838 Cr (64.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Bodhre - Dhule is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618693. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bodhre - Dhule is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.