Original Cost
₹301 Cr
Baseline estimate
Revised Cost
₹334 Cr
Latest approved cost
Expenditure
₹247 Cr
Spent to date
Utilization
73.9%
Of revised budget
Cost Status
+11.1%
+₹33 Cr increase
Remaining
₹87 Cr
Budget left
Spent
₹247 Cr
Remaining
₹87 Cr
Total
₹334 Cr
Original Cost
₹301 Cr
Revised Cost
₹334 Cr
Increase
+₹33 Cr
Escalation
+11.1%
Project Approved
Construction / Implementation
Original End Date
02/05/2023
Revised Completion
30/04/2026
Completed
Cost has increased by ₹33 Cr (11.1%) from the original estimate of ₹301 Cr.
Expenditure stands at ₹247 Cr, which is 73.9% of the revised project cost.
Remaining budget: ₹87 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.