Bijnor-Kotawali
Original Cost
₹301 Cr
Baseline estimate
Revised Cost
₹334 Cr
Latest approved cost
Expenditure
₹302 Cr
Spent to date
Utilization
90.3%
Of revised budget
Cost Status
+11.1%
+₹33 Cr increase
Remaining
₹32 Cr
Budget left
Budget Utilization
90.3%Spent
₹302 Cr
Remaining
₹32 Cr
Total
₹334 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹301 Cr
Revised Cost
₹334 Cr
Increase
+₹33 Cr
Escalation
+11.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
02/05/2023
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹33 Cr (11.1%) from the original estimate of ₹301 Cr.
Expenditure stands at ₹302 Cr, which is 90.3% of the revised project cost.
Remaining budget: ₹32 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Bijnor-Kotawali is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹301.00 Cr, later revised to ₹334.48 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Bijnor-Kotawali"?
- Bijnor-Kotawali is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹301 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹301 Cr and has been revised to ₹334 Cr — a cost overrun of +11.1%. Expenditure to date: ₹302 Cr (90.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Bijnor-Kotawali is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618925. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bijnor-Kotawali is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.