TelecommunicationIPM · Central Project#706775

BharatNet

Department of TelecommunicationsWest Bengal
Revised Cost: ₹12.7K CrUtilization: 81.2%

Original Cost

₹12.7K Cr

Baseline estimate

On budget

Revised Cost

₹12.7K Cr

Latest approved cost

Expenditure

₹10.3K Cr

Spent to date

Utilization

81.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹2389 Cr

Budget left

Budget Utilization

81.2%
0%25%50%75%100%

Spent

₹10.3K Cr

Remaining

₹2389 Cr

Total

₹12.7K Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/08/2023

Revised Completion

31/03/2019

Completed

Project Details

Project Code706775
SectorTelecommunication
MinistryDepartment of Telecommunications
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹12.7K Cr
Revised Cost₹12.7K Cr
Expenditure₹10.3K Cr
Original End Date31/08/2023
Revised Date31/03/2019

Project Intelligence

Mega infrastructure project worth ₹12.7K Cr — among the largest central projects in West Bengal.

Project is within original budget of ₹12.7K Cr — no cost escalation recorded.

Expenditure stands at ₹10.3K Cr, which is 81.2% of the revised project cost.

Remaining budget: ₹2389 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Telecommunication. Ministry: Department of Telecommunications.

BharatNet is a centrally-funded infrastructure project under Department of Telecommunications, in the Telecommunication sector. The original approved cost is ₹12709.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "BharatNet"?
BharatNet is a centrally-funded infrastructure project under the Department of Telecommunications, tracked through the Investment Project Monitoring (IPM) system. Sector: Telecommunication. State: West Bengal. Original cost: ₹12709 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹12709 Cr has not been significantly revised. Expenditure: ₹10320 Cr (81.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
BharatNet is under the Department of Telecommunications in the Telecommunication sector. Project code: 706775. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. BharatNet is one of several Bihar projects tracked under the Telecommunication sector on the IPM system.