Original Cost
₹845 Cr
Baseline estimate
Revised Cost
₹1395 Cr
Latest approved cost
Expenditure
₹587 Cr
Spent to date
Utilization
42.1%
Of revised budget
Cost Status
+65.1%
+₹550 Cr increase
Remaining
₹808 Cr
Budget left
Spent
₹587 Cr
Remaining
₹808 Cr
Total
₹1395 Cr
Original Cost
₹845 Cr
Revised Cost
₹1395 Cr
Increase
+₹550 Cr
Escalation
+65.1%
Project Approved
Construction / Implementation
Original End Date
15/09/2021
Revised Completion
30/11/2026
Completed
Cost has increased by ₹550 Cr (65.1%) from the original estimate of ₹845 Cr.
Expenditure stands at ₹587 Cr, which is 42.1% of the revised project cost.
Remaining budget: ₹808 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.