Roads & HighwaysIPM · Central Project +31.9% overrun#618696

Bellary to Byrapura Section km 253.600 to km 308.550 of NH-150A

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹1690 CrUtilization: 20.7%Overrun: +₹409 Cr

Original Cost

₹1281 Cr

Baseline estimate

+32% overrun

Revised Cost

₹1690 Cr

Latest approved cost

Expenditure

₹349 Cr

Spent to date

Utilization

20.7%

Of revised budget

Escalated

Cost Status

+31.9%

+₹409 Cr increase

Remaining

₹1340 Cr

Budget left

Budget Utilization

20.7%
0%25%50%75%100%

Spent

₹349 Cr

Remaining

₹1340 Cr

Total

₹1690 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1281 Cr

Revised Cost

₹1690 Cr

Increase

+₹409 Cr

Escalation

+31.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

23/10/2021

Revised Completion

01/09/2022

Completed

Project Details

Project Code618696
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-02

Financial Summary

Original Cost₹1281 Cr
Revised Cost₹1690 Cr
Expenditure₹349 Cr
Original End Date23/10/2021
Revised Date01/09/2022

Project Intelligence

Cost has increased by ₹409 Cr (31.9%) from the original estimate of ₹1281 Cr.

Expenditure stands at ₹349 Cr, which is 20.7% of the revised project cost.

Remaining budget: ₹1340 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Bellary to Byrapura Section km 253.600 to km 308.550 of NH-150A is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1281.00 Cr, later revised to ₹1689.60 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Bellary to Byrapura Section km 253.600 to km 308.550 of NH-150A"?
Bellary to Byrapura Section km 253.600 to km 308.550 of NH-150A is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1281 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1281 Cr and has been revised to ₹1690 Cr — a cost overrun of +31.9%. Expenditure to date: ₹349 Cr (20.7% of revised cost). Data as of 2026-02.
QWhich ministry is responsible for this project?
Bellary to Byrapura Section km 253.600 to km 308.550 of NH-1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618696. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bellary to Byrapura Section km 253.600 to km 308.550 of NH-1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.