Roads & HighwaysIPM · Central Project#617887

Beawer Gomti 4LPS from km 58.245 to km 108.600 Pkg-I

Ministry of Road Transport & HighwaysRajasthan
Revised Cost: ₹379 CrUtilization: 54.5%

Original Cost

₹379 Cr

Baseline estimate

On budget

Revised Cost

₹379 Cr

Latest approved cost

Expenditure

₹206 Cr

Spent to date

Utilization

54.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹173 Cr

Budget left

Budget Utilization

54.5%
0%25%50%75%100%

Spent

₹206 Cr

Remaining

₹173 Cr

Total

₹379 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

13/10/2023

Revised Completion

03/07/2026

Completed

Project Details

Project Code617887
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateRajasthan
Data Month2026-06

Financial Summary

Original Cost₹379 Cr
Revised Cost₹379 Cr
Expenditure₹206 Cr
Original End Date13/10/2023
Revised Date03/07/2026

Project Intelligence

Project is within original budget of ₹379 Cr — no cost escalation recorded.

Expenditure stands at ₹206 Cr, which is 54.5% of the revised project cost.

Remaining budget: ₹173 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Beawer Gomti 4LPS from km 58.245 to km 108.600 Pkg-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹379.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Beawer Gomti 4LPS from km 58.245 to km 108.600 Pkg-I"?
Beawer Gomti 4LPS from km 58.245 to km 108.600 Pkg-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Rajasthan. Original cost: ₹379 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹379 Cr has not been significantly revised. Expenditure: ₹206 Cr (54.5% of cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Beawer Gomti 4LPS from km 58.245 to km 108.600 Pkg-I is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617887. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Beawer Gomti 4LPS from km 58.245 to km 108.600 Pkg-I is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.