Original Cost
₹379 Cr
Baseline estimate
Revised Cost
₹379 Cr
Latest approved cost
Expenditure
₹179 Cr
Spent to date
Utilization
47.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹200 Cr
Budget left
Spent
₹179 Cr
Remaining
₹200 Cr
Total
₹379 Cr
Project Approved
Construction / Implementation
Original End Date
13/10/2023
Revised Completion
31/12/2025
Completed
Project is within original budget of ₹379 Cr — no cost escalation recorded.
Expenditure stands at ₹179 Cr, which is 47.3% of the revised project cost.
Remaining budget: ₹200 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.