Barauni Refinery Capacity Expansion from 6.0 to 9.0 MMTPA
Original Cost
₹14.8K Cr
Baseline estimate
Revised Cost
₹16.7K Cr
Latest approved cost
Expenditure
₹13.2K Cr
Spent to date
Utilization
79.1%
Of revised budget
Cost Status
+12.9%
+₹1914 Cr increase
Remaining
₹3503 Cr
Budget left
Budget Utilization
79.1%Spent
₹13.2K Cr
Remaining
₹3503 Cr
Total
₹16.7K Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹14.8K Cr
Revised Cost
₹16.7K Cr
Increase
+₹1914 Cr
Escalation
+12.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/04/2023
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Mega infrastructure project worth ₹16.7K Cr — among the largest central projects in Bihar.
Cost has increased by ₹1914 Cr (12.9%) from the original estimate of ₹14.8K Cr.
Expenditure stands at ₹13.2K Cr, which is 79.1% of the revised project cost.
Remaining budget: ₹3503 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.
Barauni Refinery Capacity Expansion from 6.0 to 9.0 MMTPA is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹14810.00 Cr, later revised to ₹16724.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Barauni Refinery Capacity Expansion from 6.0 to 9.0 MMTPA"?
- Barauni Refinery Capacity Expansion from 6.0 to 9.0 MMTPA is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Bihar. Original cost: ₹14810 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹14810 Cr and has been revised to ₹16724 Cr — a cost overrun of +12.9%. Expenditure to date: ₹13221 Cr (79.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Barauni Refinery Capacity Expansion from 6.0 to 9.0 MMTPA is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 701324. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Barauni Refinery Capacity Expansion from 6.0 to 9.0 MMTPA is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.