Roads & HighwaysIPM · Central Project#618478

Bangalore Chennai Expressway Phase-III Package II Walajahpet to Arakkonam from Km 180.000 to Km 204.500

Ministry of Road Transport & HighwaysTamil Nadu
Revised Cost: ₹1107 CrUtilization: 55.7%

Original Cost

₹1107 Cr

Baseline estimate

On budget

Revised Cost

₹1107 Cr

Latest approved cost

Expenditure

₹616 Cr

Spent to date

Utilization

55.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹491 Cr

Budget left

Budget Utilization

55.7%
0%25%50%75%100%

Spent

₹616 Cr

Remaining

₹491 Cr

Total

₹1107 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/07/2024

Revised Completion

31/10/2026

Completed

Project Details

Project Code618478
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTamil Nadu
Data Month2026-08

Financial Summary

Original Cost₹1107 Cr
Revised Cost₹1107 Cr
Expenditure₹616 Cr
Original End Date14/07/2024
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹1107 Cr — no cost escalation recorded.

Expenditure stands at ₹616 Cr, which is 55.7% of the revised project cost.

Remaining budget: ₹491 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Bangalore Chennai Expressway Phase-III Package II Walajahpet to Arakkonam from Km 180.000 to Km 204.500 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1107.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Bangalore Chennai Expressway Phase-III Package II Walajahpet to Arakkonam from "?
Bangalore Chennai Expressway Phase-III Package II Walajahpet to Arakkonam from Km 180.000 to Km 204.500 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹1107 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1107 Cr has not been significantly revised. Expenditure: ₹616 Cr (55.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Bangalore Chennai Expressway Phase-III Package II Walajahpe is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618478. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bangalore Chennai Expressway Phase-III Package II Walajahpe is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.